|
Hardware/Equipment and Systems
Installation
Checking the customers premises for suitability
This section is only for new installs, if you are
repairing a machine or one of its peripherals
these procedures will have already been carried out. It
will depend on the size of the machine to be installed how many of the following
installation items are looked at. For example, if a simple desktop PC
is being installed there only needs to be a desk that will support its weight
and the required services nearby to connect to, for
example, network and mains power. If a
mainframe computer is being installed all of the following items
will need to be checked. Before any
installation or upgrade to systems can take place it must be established
that the environment and facilities are suitable for the relevant hardware
installation. The main points which need to
be established are:
- Is there space for the new hardware? - this
must include space for operation, future
access for maintenance and health and safety considerations.
- Is the building structure able to cope with
the increased weight of equipment? - this
includes ensuring whether the floor requires strengthening
etc.
- Does the identified location allow connection
to the existing system? - be aware of the
length of interface cables, under floor cable
runs etc.
- Is electrical power available, adequate and
appropriate for the equipment? - there
must be no trailing cables, are there correctly rated
circuit breakers, single or three phase supply.
- Will the ventilation or air conditioning
systems be sufficient when the new
equipment is installed? - will the heat output from the equipment
require the adjustment of existing, or installation of additional
air conditioning equipment, or cause the working environment
to become uncomfortable if no air conditioning is in use?
- Does the equipment require clean room
conditions?
- Will the equipment fit through doors, lifts,
stairs etc? - does it require removal of
door frames, windows etc?
- Will specialist lifting equipment or expertise
be required? - cranes, specialist
removers, glaziers, carpenters, police, local authority etc.
- Can the delivery vehicles gain access to the
premises? - are there parking
restrictions that apply? Is the loading bay able to accommodate
the vehicle(s)?
- Can the delivery and installation staff gain
entry to the premises at the required
times? - Have the necessary security arrangements been
made? Are site passes required? Will security systems allow access
to all areas required?
- Can health and safety requirements be
maintained at ALL times during the
installation? A risk assessment should be carried out to ascertain
any dangers to your firms employees, your customers employees
or anyone using the building or area.
If the answer to any of these is
NO or there are other extraordinary circumstances,
then the installation cannot proceed until all the issues raised
are resolved.
|